West Dam will be reconstructed in three phases:

PHASE 1: Complete! Build a pilot channel, breach the dam and install sediment erosion control devices

PHASE 2: Material removal. 86,000 cubic yards of silt and material dug out, along with old dam removal and mass grading. This could begin in February 2025 and be completed by May 2025

Phase 2 Drone Footage

April 15th 2025
April 23rd 2025

PHASE 3: Dam Construction. This could start in the Fall of 2025 and be completed by Summer 2026